Project information
Position on ancillary services of Endesa in Iberia
November 2020 - December 2020
Funding entity Endesa Generación S.A
This work is aimet at investigating the position on ancillary services of Endesa in Iberia in 2030.
Research topics:
- Steady-state: Load flows, analysis of power system constraints, optimal load flows, voltage control ancilliary service,short-circuits, protections in transmission and ditribution networks
- Stability: Large disturbance stability, tuning of frequency loadshedding schemes, excitation control, small disturbance stability, tuning of power system stabilizers, identification of AVR and governor models
EndesaPosicionamientoSSCCIberia